Cost estimate: when is it binding in Germany?

As IHK Köln explains, a cost estimate does not guarantee a price unless the parties have agreed otherwise: whether the amount binds depends on the contract. If a substantial overrun becomes foreseeable, § 649 BGB requires you to inform your customer without delay. Your price agreement, timely conversations about extra costs and a clear agreement on any preparation fee therefore matter.
What is a cost estimate?
A cost estimate calculates the likely cost of the planned work before an order is placed, as IHK Frankfurt am Main explains. It helps your customer decide whether to place the planned order. In the overview of invoices, it belongs among the documents relating to an order before the work is billed.
This guide covers the ordinary contract for work and services. Under § 631 Bürgerliches Gesetzbuch (BGB), you promise a specific result, and your customer owes the agreed remuneration. That result can also come from a service. Project-based work may therefore fall within this category; general ongoing advice is not automatically the same case.
The classification concerns the contract. It does not depend on whether your activity is a Freiberufler or a Gewerbe, on the label Kleingewerbe, or on your VAT status. This article does not cover special medical fee schedules, insurance valuations or specific building rules. First check whether your order falls within the scope described here.
According to IHK Frankfurt, an accepted binding quote sets the price for the work it describes. An invoice, by contrast, bills for a supply or other service under § 14 Abs. 1 Umsatzsteuergesetz (UStG). The heading alone does not determine the legal effect. The overview of documents before an invoice explains how a cost estimate, quote and pro forma differ.
Is a cost estimate binding?
According to IHK Köln, whether the stated price is binding depends on the specific agreement; an ordinary cost estimate does not automatically guarantee it. What matters is which obligation you actually accepted and what work it covers.
An ordinary cost estimate focuses on the expected amount of the costs. An express guarantee that the amount is correct changes how the price risk is assessed. § 649 BGB specifically governs a contract based on a cost estimate whose accuracy you have not guaranteed. Its rules on substantial overruns are therefore not a general way out of every price commitment.
An accepted binding quote must in turn be considered in light of the work it describes. IHK Frankfurt explains that the stated price is then binding for that work. Whether something different or additional is commissioned later is a separate question. A price agreement should therefore always be read together with its scope of work.
Before the order, clarify whether you are stating estimated costs or promising a binding price. Also record which work the statement covers. This is a practical recommendation so that both sides have the same basis for their decision. A heading such as “cost estimate” alone does not resolve the question.
Distinguish an agreement on binding remuneration from an express guarantee of the calculation. Not every wording leads to the same mechanism. If the statement or its scope remains unclear, have the specific contract reviewed before relying on the document’s label alone to justify a later additional charge.
What happens if the costs increase?
If a substantial overrun is expected under a contract based on a cost estimate without a price guarantee, § 649 Abs. 2 BGB requires you to inform your customer without delay. The relevant point is when the change becomes apparent while the work is under way, not when you issue the final invoice.
According to Handwerkskammer Frankfurt-Rhein-Main, your customer generally has to accept an insignificant overrun. That does not create a fixed reserve that you may add to every estimate. IHK Köln stresses that there is no universally applicable percentage. Whether an overrun is substantial depends on the circumstances of the individual order.
A percentage is not a general permission to charge extra costs. First check your price agreement and inform your customer as soon as a substantial overrun becomes foreseeable. A price guarantee cannot be bypassed with a flat surcharge.
For the conversation, this order can help:
- Explain without delay why the current calculation is unlikely to be enough and what changed costs to expect. Do not wait until the final bill to send the message.
- Separate a mistaken estimate of the original work from additional work your customer has requested. The Handwerkskammer treats additional requests separately; they should not simply be included in the same comparison with the original scope.
- Record whether your customer wants to continue the order or terminate it because of the substantial overrun. Keeping a record is a practical recommendation for clarity, not a claim that the law requires a particular written form here.
If your customer continues with the order, the remuneration may exceed the cost estimate, according to IHK Frankfurt. The remuneration agreement and any separate questions of damages still matter. Continuing therefore does not automatically release you from the consequences of culpably failing to send a required notice.
If your customer terminates because of the substantial overrun, § 649 Abs. 1 BGB refers to § 645 Abs. 1 BGB for your claim. This concerns the part of the remuneration corresponding to work already done and expenses not included in it. That does not automatically mean the full contract price or that the work is automatically unpaid.
According to the Handwerkskammer, someone who culpably fails to give the required notice may be liable for the resulting loss. The loss caused by the breach of duty is what matters. The entire difference from the original amount does not automatically disappear.
Example: work estimated at €1,000
You estimated €1,000 for the agreed work. While carrying it out, you discover additional effort that is likely to result in substantial extra costs. Tell your customer promptly about the cause and expected costs, and clarify whether to continue. The example sets no euro threshold for what counts as substantial. If your customer also wants additional work, document that expansion separately from the extra effort for the original work.
Can you charge for a cost estimate?
According to Handwerkskammer Frankfurt-Rhein-Main, under § 632 Abs. 3 BGB a cost estimate is presumed not to be remunerated; IHK Frankfurt says an expressly agreed preparation fee is possible. The fee for the calculation and the remuneration for carrying out the later work are two separate questions.
If you want to charge for the preparation, agree the fee individually before you begin. IHK Frankfurt points out that you must be able to prove the relevant agreement. So keep a clear record of what preparation was agreed and what it will cost. The recommendation to document it does not mean the law always requires a particular written form.
Discuss a preparation fee before drawing up the estimate and record the individual agreement. That lets your customer decide whether to pay for the preparation before you start the work.
Do not rely on a general clause in your terms and conditions alone for the fee. The Handwerkskammer and IHK Frankfurt describe its permissibility with different degrees of strictness; IHK discusses a disputed assessment and the possibility of customary practice in the industry. This does not amount to a general assurance that such a clause secures your remuneration. A clear individual agreement is the practical recommendation here.
According to IHK Frankfurt, commissioned creative work may already be the actual work itself, such as developing a layout. It should be distinguished from a simple preliminary cost estimate. For a separate diagnosis, also clarify which work was commissioned and what remuneration you agreed. Not every inspection or creative preliminary idea automatically becomes chargeable just because of its label. So first ask what service was actually commissioned.
Frequently asked questions
What is a cost estimate?
According to IHK Frankfurt, a cost estimate calculates the expected costs before an order is placed. It helps you assess the planned scope of work and expected costs. It does not automatically guarantee a price. Whether the amount is binding depends on the specific agreement between you and your customer.
Is a cost estimate binding?
According to IHK Köln, whether a cost estimate contains a binding price depends on the agreement in the individual case. An ordinary cost estimate does not automatically guarantee the amount. An expressly assumed price guarantee must be assessed differently. An accepted binding quote, by contrast, sets the price for the work it describes.
Can a cost estimate be exceeded?
With an ordinary cost estimate that has no price guarantee, extra costs are possible; according to IHK Köln, there is no universally applicable permitted percentage. As soon as a substantial overrun is expected, § 649 BGB requires you to inform your customer without delay. Whether the customer continues or terminates the contract as a result affects the remuneration; any possible questions of damages must be assessed separately.
Do I have to charge for a cost estimate?
According to Handwerkskammer Frankfurt-Rhein-Main, under § 632 Abs. 3 BGB a cost estimate is presumed not to be remunerated. IHK Frankfurt says an expressly agreed preparation fee is possible. So clarify individually in advance whether a fee applies and how much it is. Remuneration for the later work is a separate matter.